Restoration/Renovation

Mass Bay Completes Electrical Reno

(above and below) The new Forest Hills Station upper busway canopy features custom Lumenpulse main fixtures, WE-EF decorative LED lighting, and variable message information display systems.

Boston – Mass Bay Electrical Corp., based in East Boston, has completed all electrical and lighting installations associated with the MassDOT’s Casey Arborway renovation project at Forest Hills Station Upper Busway Canopy.

The NECA Boston contractor met the fast-track, compressed schedule beginning on November 1, 2018 and completing the project by mid-April 2019.

Project executive Rick Broderick, project manager Mike Walsh and foreman Chris Boyer headed the project team, managing a crew of seven IBEW Local 103 electricans, working in close coordination with the project’s architectural engineering firm AECOM and general contractor of Boston, and Barletta Heavy Division of Canton.