Healthcare MEP

F&T Leads Design Team for Hospital Utility Plant

IMG_3146

The new Concord Hospital central utility plant / photo by Fitzemeyer & Tocci

 

Concord, NH – Concord Hospital selected Fitzemeyer & Tocci (F&T) to lead the design team for Concord Hospital’s new central utility plant. The F&T team coordinated the work of several consultants, while also working collaboratively with the hospital’s construction manager. F&T provided HVAC, plumbing, fire protection and electrical engineering design, and construction administration services for the new central utility plant. The project consisted of replacing the existing smaller plant with a new 9,000sf, two-level steam boiler and chiller plant. Lavallee Brensinger Architects was the project architect.

 

 

IMG_3191

photo by Fitzemeyer & Tocci

The new building was constructed while keeping plant building No. 1 and the Concord Hospital fully operational at all times. It was requested that current equipment in the existing boiler room be reused and incorporated into the design of the new plant. This included the main hospital’s condensate receiver and fuel oil pumping system. Utilizing Revit, the design team was able to closely coordinate the boilers and flue stack, boiler cat-walk, chillers, pumps, cooling towers, floor and trench drains, dry pipe sprinkler system, domestic water system, natural gas piping and meter, main electrical switchgear, panel boards, VFDs and major conduits, storm and sanitary waste piping. The existing pad-mounted transformer was reused and mounted on the roof on a specially preconstructed structural curb. The design team, contractor, and owner worked closely to locate service feeders to and from the transformer, avoiding interference with the large steam piping and boiler flue within the boiler room below. New electrical feeders were connected to the existing paralleling switchgear while minimizing impacts and disruptions to normal hospital operations. The relocation of existing chillers and cooling towers was accomplished during the lower load periods of the year, and the cooling system was brought back up to full capacity in time to meet the peak demand season.