Municipal Northern New England

North Branch Completes Steel Erection at Laconia Central Fire Station

04142015 Laconia Fire Department Steel Erection Complete - Photo #1

Steel erection complete

Warrenstreet Architects

Laconia, NH – North Branch Construction of Concord has completed the erection of structural steel for the new administrative portions of the Laconia Central Fire Station on 848 North Main Street in Laconia.

Design for the project is provided by Warrenstreet Architects of Concord.

Concrete slabs, exterior metal framing, envelope systems, and light-gauge metal-framed roof trusses will begin in the upcoming weeks.

Construction includes the renovation of approximately 13,200sf of the existing two-story CMU block and steel framed building and the addition of an approximately 13,000sf, two-story steel-framed building with brick and PVC trimmed façade to house new administrative offices, dormitory facilities, an emergency operations center training facility, and additional vehicle storage.

The fire station remains in full service throughout the extensive renovations.

Construction underway.

Construction under way

Construction is on track to be complete by December.