JMB Completes Electrical Fit-Out of BCG Offices

Teams with Turner Construction, GC

200 Pier 4 office building

Boston – J&M Brown Company, Inc. (JMB), based in Jamaica Plain, recently completed the fast-track electrical fit-out of The Boston Consulting Group’s (BCG) new 184,000sf offices at the new 200 Pier 4 office building in Boston’s Seaport district. The project comprised JMB’s installation of the electrical distribution system, fire alarm system, lighting, and lighting control systems.  

 
The NECA Boston Chapter contractor furnished and installed the extensive lighting package, which consisted of more than 1,300 fixtures. State-of-the-art Creston lighting controls are also installed throughout the six-and-a-half floors occupied by BCG. 
 

Five-story internal stairwell

The fire alarm scope included integration/syncing of the system with the base building fire alarm system as well as installation of fire curtain protection in a five-story internal stairwell.

 
The JMB project team supervised a field crew of 32 IBEW Local 103 electricians at peak construction in the aggressive nine-month project schedule. 
 
Boston Consulting Group is the anchor tenant, occupying floors seven through 13 at the new 13-story 220 Pier 4 building. BCG moved 700 employees into the facility in June 2018. 

Ring fixtures